In order to feed the electricity generated by the wind farm into the national distribution network, an onshore grid connection is required between the landfall point at Weybourne and a suitable connection point.
The onshore grid connection project consists of two main components:
The cable system was completed in late 2010; it comprises six power cables installed below ground in plastic pipes or ‘ducts’. Fibre optic cables for communication purposes were installed at the same time. Along most of the route the cables were installed using a method of open-cut trenching , the trenches being around 2.2m wide and 1.6m deep.
The majority of land along the cable route is cultivated agricultural land separated by hedgerows and occasional trees. Agreements were reached with local landowners before the work could proceed.
The route crosses the local road network in 14 locations and local landmarks such as the North Norfolk Railway [Poppy Line], the River Bure, several areas of woodland and the Kelling Heath holiday park. In these locations open trenching was not appropriate, and a technique known as ‘direction drilling’ was used to install the cable ducts, thereby minimising surface impact.
The construction of the new substation was also completed in late 2010, and the main commissioning leading up to the energising of the substation by UK Power Networks took place during the early months of 2011.