Project Schedule

 
 



On this page you find the planning for the consent process and development of the Sheringham Shoal Offshore Wind Farm.

 

Project schedule

The proposed programme for the development of our offshore wind farm is as follows:

Consenting process 2006-2007
Detailed design, procurement and contracting 2006-2008
Onshore construction activity 2009-2010
Offshore construction activity
2010-2011